Arkansas annual solar electricity generationYears 2001 through 2026. Published annual generation points cover 2014 through 2025. Total solar includes EIA estimates for small-scale systems. Values are in gigawatt-hours. Missing years are not plotted as zero. Focus or select a point to read its value.03,0006,0002014: 4.853 GWh2015: 6.339 GWh2016: 33.201 GWh2017: 40.708 GWh2018: 225.179 GWh2019: 245.76 GWh2020: 358.389 GWh2021: 631.056 GWh2022: 966.735 GWh2023: 1,194.034 GWh2024: 2,840.328 GWh2025: 5,316.282 GWhNo annual total in this seriesbefore 2014.Arkansas annual solar electricity generationAnnual chart for 2014 through 2025. Published annual generation points cover 2014 through 2025. Total solar includes EIA estimates for small-scale systems. Values are in gigawatt-hours. Missing years are not plotted as zero. Focus or select a point to read its value.03,0006,00020142018202220252014: 4.853 GWh2015: 6.339 GWh2016: 33.201 GWh2017: 40.708 GWh2018: 225.179 GWh2019: 245.76 GWh2020: 358.389 GWh2021: 631.056 GWh2022: 966.735 GWh2023: 1,194.034 GWh2024: 2,840.328 GWh2025: 5,316.282 GWh
20255,316.282 GWhTotal solar · includes EIA small-scale estimates
Total solar (EIA estimate)

Published annual generation, not installed capacity or a forecast. Total solar includes EIA’s estimates for small-scale systems. The time alignment provides context; it does not establish that an event caused a change in generation.

Follow a thread. Check a source.

Read every timeline event
  1. Policy & tax

    Arkansas establishes net metering

    April 19, 2001 — legislation approved

    Act 1781 established Arkansas's renewable-energy net-metering framework. The act expressly states an October 1, 2001 effective date. Original act, §§1,4–5 A policy milestone, not a date for the state's first solar installation.

  2. Policy & tax

    Net-metering rules take shape

    July 26, 2002 — revised rules approved

    PSC Order 4 approves revised rules and directs conforming utility filings. It follows the earlier July 3 adoption referenced in Order 4.

  3. Solar projects

    Residential solar is documented

    2011 — residential survey record

    EIA's 2011 file lists 42 residential photovoltaic net-metering customers for Entergy Arkansas. EIA archive, Net_Metering_2011.xlsx, States row 10 One utility's reported customer count; not all Arkansas homes or systems.

  4. Policy & tax

    Net-metering credit can carry forward

    April 12, 2013 — legislation approved

    Act 1221 allows a limited amount of unused net-metering credit to carry into the next annual billing cycle. The added carryover is bounded by four months’ average usage for the closing cycle.

  5. Perihelion

    Perihelion Solar begins in Russellville

    2017 — founding year

    Arkansas Tech University’s published panelist biography records Perihelion Solar as founded in 2017 and based in Russellville.

  6. Solar projects

    Solar at the North Little Rock factory

    2017 — company reporting year

    L'Oréal's 2017 report documents an installed solar array at its North Little Rock plant. Company report, p.6 1.2 MW as reported; the cited passage does not label AC or DC. No exact commissioning day is supplied.

  7. Perihelion

    Perihelion's first rooftop and ground arrays

    January 2018 — first installations

    Perihelion's first installations were founder Andrew Barrett's home rooftop array and Bruce Tedford's ground-mounted array. The two projects began the company's hands-on installation history in Arkansas.

    Source note: Perihelion company history, confirmed by founder Andrew Barrett in November 2026. January 2018 is the installation month; no exact day is assigned.

  8. Solar projects

    Clarksville celebrates its solar project

    January 24, 2018 — ribbon-cutting

    Clarksville's utility records the ribbon-cutting for its Scenic Hill Solar partnership. Utility project account The 2017 developer announcement described a planned 5 MW AC / 6.5 MW DC plant and utility power purchases. The ribbon date alone does not establish commercial operation.

  9. Policy & tax

    Leases and service contracts expand

    March 14, 2019 — legislation approved

    Act 464 broadened the net-metering customer definition to include qualifying leases and certain qualifying service contracts for tax-exempt entities, and addressed storage. Original act, §1 and approval Contract and eligibility conditions apply; the act and implementing rules have separate dates.

  10. Perihelion

    A downtown Russellville office

    By September 20, 2020 — downtown office open

    Perihelion opened an office on West B Street in downtown Russellville, giving customers a local place to meet the team and discuss solar projects.

    Source note: Perihelion company correspondence documents the office open by September 20, 2020. That is a dated record of operation, not an exact opening day.

  11. Perihelion

    Perihelion installs All Saints’ solar

    2021 — original installation year

    Perihelion installed the original rooftop array at All Saints' Episcopal Church in Russellville. Project story 68.4 kW DC, with REC modules and Enphase IQ7+ microinverters documented in the installation records.

  12. Solar projects

    Searcy pairs solar and storage

    January 2022 — reported initial commercial-operation month

    Matched EIA records identify Searcy Solar Hybrid's solar and battery generators. Entergy announced the facility online on January 28. EIA 2022 records, plant 62617 Solar: 100 MW AC / 145.2 MW DC. Battery: 10 MW / 30 MWh. The announcement date does not supply an exact commissioning day.

  13. Perihelion

    Room for equipment and installation work

    2022 — Phoenix Avenue warehouse expansion

    Perihelion added its Phoenix Avenue warehouse in Russellville as a base for solar equipment and installation work. The property later became the company's combined office and warehouse.

    Source note: Perihelion company correspondence from May and June 2022 describes the new Phoenix Avenue warehouse. No exact opening day is assigned.

  14. Policy & tax

    The residential credit becomes 30%

    August 16, 2022 — Inflation Reduction Act

    The Inflation Reduction Act changes the residential clean energy credit to 30% for qualifying property beginning in 2022. This is a historical tax change; the later 2025 termination is a separate event below.

  15. Policy & tax

    Act 278 changes the framework

    March 13, 2023 — legislation approved

    Act 278 amended the state's net-metering framework and set deadlines for revised-rule submission and utility rate-schedule changes. Original act, §§3–4 Legislation, rules and a customer's applicable utility tariff remain distinct.

  16. Policy & tax

    PSC adopts amended rules

    September 29, 2023 — rule amendments adopted

    The PSC adopted amendments following Act 278 in docket 23-021-R, Order 7. Order, pp.196–198 The order conditions effectiveness on later approvals. September 29 is the adoption date; this account does not assign an unverified effective day.

  17. Solar projects

    Woodruff County Solar enters service

    October 2024 — reported initial commercial-operation month

    EIA identifies Woodruff County Solar near Augusta; AECC's fleet account corroborates the operating year and AECC ownership. EIA 2025 records, plant 66282 / PV1 122 MW AC / 148.94 MW DC. This is separate from the similarly named Woodruff Electric Cooperative facility in St. Francis County.

  18. Policy & tax

    The legacy retail-credit window closes

    Before September 30, 2024 — legacy qualification boundary

    Qualifying actions for legacy status had to meet the requirements in 23 CAR §457-206 before September 30, 2024. Qualifying facilities retain the prior rate structure, subject to the rule’s conditions, until June 1, 2040. The transition did not end the legacy status of every existing system; account and facility records still matter.

  19. Perihelion

    Panel-to-inverter wiring at Morrilton

    May 2025 — project fieldwork

    Perihelion took part in its first industrial-scale solar-array project, partnering with Stellar Sun Solar on the City of Morrilton array. Perihelion's team completed the wire connections from all panels to the inverters.

    Source note: Perihelion's original field photographs are dated May 2025. Founder Andrew Barrett confirmed the company's first industrial-scale project participation and its panel-to-inverter wiring scope in November 2026. The photo dates do not assign a commissioning day.

  20. Perihelion

    One home for the office and warehouse

    2025 — office and warehouse brought together

    Perihelion closed its downtown office and moved the office into its Phoenix Avenue warehouse, bringing customer conversations, administration and installation operations together at one location.

    Source note: Perihelion company history, confirmed by founder Andrew Barrett. A September 17, 2025 company-address notice corroborates the move to the warehouse; it does not establish the exact physical moving day.

  21. Policy & tax

    The home clean-energy credit reaches its cutoff

    December 31, 2025 — residential credit expenditure cutoff

    Public Law 119-21 shortens the life of the residential §25D credit. IRS guidance excludes expenditures made after December 31, 2025 and treats original installation completion as the expenditure date. Paying before the cutoff does not qualify an installation completed afterward. This event concerns the residential §25D credit.

  22. Perihelion

    Solar maintenance for City Corporation

    2026 — first solar-array maintenance contract

    Perihelion established its first solar maintenance contract with City Corporation for the array serving Russellville's water-treatment operations. The relationship covers separately authorized solar field services and technical support as needs arise.

    Source note: Current company history confirmed by founder Andrew Barrett in November 2026. No exact contract signature or service-start date is assigned. The service relationship does not imply continuous monitoring or guaranteed emergency coverage.

  23. Perihelion

    Engineering and long-term solar care

    November 2026 — company focus documented

    Perihelion’s company page describes its maintenance and engineering focus so existing customers can continue to rely on support. It also clarifies that the customer profit-sharing program discussed in earlier coverage was never implemented.

Generation data and methods

EIA annual Arkansas data, all sectors. The published total includes utility-scale solar and estimated small-scale photovoltaic generation. One GWh equals 1,000 MWh. These points cover 2014–2025; earlier years and 2026 are left unplotted.

Arkansas annual solar generation (GWh)
YearTotal, estimatedUtility-scaleSmall-scale, estimated
20144.853Not supplied4.853
20156.3390.9275.412
201633.20126.1427.059
201740.70830.8129.897
2018225.179203.41321.766
2019245.76210.33335.428
2020358.389272.14886.242
2021631.056462.281168.775
2022966.735736.481230.254
20231,194.034797.523396.511
20242,840.3282,329.09511.238
20255,316.2824,737.101579.182

Source: EIA Electricity Data Browser, annual Arkansas solar series. The Electric Power Annual solar table reports the total and estimated small-scale categories; historical state generation records corroborate the utility-scale component. Sources reviewed November 14, 2026. Missing values remain missing, and no household production was calculated from a utility-scale plant’s capacity.

Selected milestones, with gaps still to fill. Policy notes describe historical changes; individual utility terms and tax eligibility need their own current review.

The next chapter is the system you own.

Keep Arkansas solar working.

Explore Perihelion’s projects, maintenance and engineering support.

Service an existing system Meet Perihelion